Performance of North Anchorage Excavation of Fuma Yangtze River Bridge in Wanzhou, China
Ran, T.1,2; Dai, F. C.3; Mei, S. H.4; Wang, W. W.5; Tan, L. H.5
刊名JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES
2019-06-01
卷号33期号:3页码:11
关键词Anchorage excavation Ground movements Deflections Prestress Field monitoring
ISSN号0887-3828
DOI10.1061/(ASCE)CF.1943-5509.0001289
英文摘要To ensure the safety of constructing the north anchorage excavation of Fuma Yangtze River Bridge, an extensive instrumentation program was carried out to monitor the performance of the excavation. This monitoring effort included the ground movements of soil outside the excavation zone, ground movements of the tops of piles, lateral deflections of piles, and prestress in cables. Based on an analysis of the monitoring data, the following findings were obtained: shallow landslides were induced by rainfall at several locations outside the excavation zone, and the movement directions of soil were consistent with the natural terrain. The horizontal displacements of the west and east top beams were generally larger than that of the north side. The vertical movements of the tops of the piles exhibited heave initially and then transitioned into settlement. The deflected profiles of the piles were similar, and the maximum lateral pile deflections were very close. The measured deformations and internal forces of the support system did not exceed the alarm values, which suggested that the excavation was in a stable state.
WOS关键词GROUND MOVEMENTS ; DEEP EXCAVATION ; WALL
WOS研究方向Construction & Building Technology ; Engineering
语种英语
出版者ASCE-AMER SOC CIVIL ENGINEERS
WOS记录号WOS:000458903100001
内容类型期刊论文
源URL[http://ir.iggcas.ac.cn/handle/132A11/90683]  
专题地质与地球物理研究所_其他部门
通讯作者Ran, T.
作者单位1.Chinese Acad Sci, Inst Geol & Geophys, 19 Beitucheng Western Rd, Beijing 100029, Peoples R China
2.Univ Chinese Acad Sci, 19 A Yuquan Rd, Beijing 100049, Peoples R China
3.Beijing Univ Technol, Coll Architecture & Civil Engn, 100 Pingleyuan, Beijing 100024, Peoples R China
4.Zhongnan Engn Co Ltd, Engn, Power China, 16 Guitangxiangzhang Eastern Rd, Changsha 410014, Hunan, Peoples R China
5.CCCC First Highway Engn Co Ltd, 15-19 Floors Shitong Int Bldg, Beijing 100024, Peoples R China
推荐引用方式
GB/T 7714
Ran, T.,Dai, F. C.,Mei, S. H.,et al. Performance of North Anchorage Excavation of Fuma Yangtze River Bridge in Wanzhou, China[J]. JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES,2019,33(3):11.
APA Ran, T.,Dai, F. C.,Mei, S. H.,Wang, W. W.,&Tan, L. H..(2019).Performance of North Anchorage Excavation of Fuma Yangtze River Bridge in Wanzhou, China.JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES,33(3),11.
MLA Ran, T.,et al."Performance of North Anchorage Excavation of Fuma Yangtze River Bridge in Wanzhou, China".JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES 33.3(2019):11.